Traffic

Major, Years-Long Project on Kennedy Expressway Will Impact Drivers Starting Next Month

Officials said "major travel delays are anticipated" and "alternative routes are strongly encouraged"

NBC Universal, Inc.

A major project is slated to take over a prominent part of the Kennedy Expressway for multiple years, impacting many Chicago-area commuters in a matter of weeks as officials urge drivers to find “alternative routes,” NBC 5’s Patrick Fazio reports.

A major project is slated to take over a prominent part of the Kennedy Expressway for multiple years, impacting many Chicago-area commuters in a matter of weeks as officials urge drivers to find "alternative routes."

The $150 million project is set to begin on March 20, beginning at the Edens Expressway junction and continuing to Ohio Street, the Illinois Department of Transportation announced Tuesday.

Officials said "major travel delays are anticipated" and "alternative routes are strongly encouraged."

The project will involve rehabbing 36 bridge structures and the reversible lane access control system, replacing overhead sign structures, installing new signs and LED lights, patching pavement, painting structures and repainting Hubbard's Cave from Grand Avenue to Wayman Street.

The work is expected to be done in three stages beginning in March and continuing through 2025.

Stage 1

The first stage will affect the inbound Kennedy, closing two main lanes of the expressway at a time, though reversible express lanes "will remain open in the inbound direction."

"Motorists should expect lane shifts and overnight lane closure, along with various ramp closures," IDOT said in a release.

Project engineers told NBC 5 traffic reporter Kye Martin that first to close will be the two left inbound lanes, which will close from March to July. Then, the two right inbound lanes will be blocked from July to November with open paths to exit and enter at all exits. On weekends and overnight, exit closures are probable.

This summer, painting and new lighting installation will begin on inbound Hubbard's Cave, between Ohio and Lake Streets. That work is expected to be completed this fall, with all lanes and ramps reopening and the express lanes resuming normal operations at that time.

Stage 2

The second stage will see changes for the reversible express lanes, which will be closed beginning in spring 2024 and is slated to be completed in fall of 2024. In addition, mainline lane closures will also be seen in both directions of Hubbard's Cave between Ohio and Lake Streets.

Stage 3

The third stage will see the reversible express lanes open in the outbound direction while two main outbound lanes of the roadway will be closed at a time.

"Lane shifts and overnight lane closure, along with various ramp closures will be needed to complete the work," the Illinois Department of Transportation said.

Additionally, outbound Hubbard's Cave between Ohio and Lake streets will be impacted.

This stage is slated to begin in spring 2025 and finish in late fall 2025.

"Motorists should expect significant delays and allow extra time for trips through this area," IDOT said in a release.

The Kennedy Expressway has been officially open since November 1960, but according to IDOT, the last major rehab project on the roadway was completed in 1994.

"The project will improve safety, traffic flow and reliability for the more than 275,000 motorists who use the expressway each day," the agency said.

Exit mobile version